Contents
1.1
Purpose of the Report
1.2
Structure of the Report
2.1
Background
2.2
General Site Description
2.3
Major Activities Undertaken
2.4
Project Organisation and
Management Structure
2.5
Status of Environmental
Approval Documents
3
Environmental
Monitoring and Audit Requirements
3.1
Environmental Monitoring
3.1.1
Air Quality
3.1.2
Odour
3.2
Site Audit
3.2.1
Water Quality
3.2.2
Landscape and
Visual
4.1
Air Quality
4.1.1
Operation Phase
Monitoring
4.2
Odour
4.2.1
Operation Phase
Monitoring
4.3
Water Quality
4.3.1
Operation Phase
Monitoring
4.4
Waste Management
4.4.1
Operation Phase
Monitoring
5.1
Environmental Site Audit
5.1.1
Operation Phase
5.2
Landscape and Visual Audit
6
Environmental Non-conformance
6.1
Summary of Environmental
Non-Compliance
6.2
Summary of Environmental
Complaint
6.3
Summary of Environmental
Summon and Successful Prosecution
7.1
Key Issues for the Coming
Reporting Period
LIST
OF TABLES
Table 2.1 Summary of Activities Undertaken in the
Reporting Period
Table 2.2 Summary of Environmental Licensing,
Notification and Permit Status
Table 3.1 Sampling and Laboratory Analysis Methodology
Table
3.2 Emission Limit for CAPCS Stack
Table
3.3 Emission Limit for CHP Stack
Table
3.4 Emission Limit for ASP Stack
Table
3.5 Emission Limit for Standby Flaring
Gas Unit
Table
3.6 Odour Intensity Level
Table
3.7 Action and Limit Levels for Odour
Nuisance
Table
3.8 Event and Action Plan for Odour
Monitoring
Table 4.1 Hourly Average of Parameters Recorded for
CAPCS
Table 4.2 Hourly Average of Parameters Recorded for
CHP 1
Table 4.3 Hourly Average of Parameters Recorded for
CHP 2
Table 4.4 Hourly Average of Parameters Recorded for
CHP 3
Table 4.5 Hourly Average of Parameters Recorded for ASP
Table 4.6 Results of the Discharge Sample Collected
from the Effluent Storage Tank in December 2021
Table 4.7 Results of the Discharge Sample Collected
from the Effluent Storage Tank in January 2022
Table 4.8 Results of the Discharge Sample Collected
from the Effluent Storage Tank in February 2022
Table 4.9 Results of the Discharge Sample from the
Petrol Interceptor 1 on 9 December 2021
Table 4.10 Results of the Discharge Sample from the
Petrol Interceptor 1 on 16 February 2022
Table 4.11 Results of the Discharge Sample from the
Petrol Interceptor 2 on 9 December 2021
Table 4.12 Results of the Discharge Sample from the
Petrol Interceptor 2 on 16 February 2022
Table 4.13 Quantities of Waste Generated from the
Operation of the Project
LIST
OF ANNEXES
Annex E Environmental complaint,
Environmental Summons and Prosecution Log |
EXECUTIVE SUMMARY
The
construction works of No. EP/SP/61/10 Organic Resources Recovery Centre
Phase 1 (the Project) commenced on 21 May 2015. This is the 27th quarterly
Environmental Monitoring and Audit (EM&A) report presenting the EM&A
works carried out during the period from 1 December 2021 to 28 February 2022 in
accordance with the EM&A Manual. Substantial completion of the
construction works was confirmed on 3 December 2018. In the meantime, the
operation phase EM&A programme had commenced in March 2019.
Substantial Completion in respect of substantial part of the Works was
confirmed on 24 February 2020. The construction phase EM&A programme
was completed in the end of February 2020.
Summary
of Works undertaken during the Reporting Month
Works
undertaken in the reporting month included:
·
Operation of the Project, including organic waste
reception, and operation of the pre-treatment facilities, anaerobic digesters,
composting facilities, air pollution control systems, on-line emission
monitoring system for the Centralised Air Pollution Control Unit (CAPCS),
Co-generation Units (CHP)s and Ammonia Stripping Plant (ASP), and the
wastewater treatment plant; and
·
Process fine-tune, including adjustment of the ASP
with new treatment media, modification of Continuous Environmental Monitoring
System (CEMS) and Supervisory Control and Data Acquisition System (SCADA)
rectification and improvement works following equipment failures and the
alteration of different operation modes and measures to adapt to the high
variation of SSOW nature and sources.
Environmental Monitoring and Audit
Progress
Air
Quality Monitoring
Exceedances
on NOx and SO2 from CHP
3 and dust, CO, NOx, SO2, VOCs and NH3 from ASP were
recorded on the on-line monitoring system from December 2021 to February 2022. It should
be noted that measurements recorded under abnormal operating conditions, e.g. start up and stopping of stacks, unstable operation,
test runs and interference of sensor, are disregarded.
In
December 2021, the exceedances of NOx, VOCs and NH3 from ASP occurred due to
system instability caused by blockage of the stripping column. The
exceedances of SO2 from the desulphurisation system for CHP and ASP were caused
by blockage of the hot water system. In January 2022, the exceedances of
NOx from CHP 3 occurred due to insufficient feedstock. The exceedance of
CO, NOx, VOCs and NH3 from ASP occurred due to system instability caused by the
malfunctioning of the steam generator. In February 2022, the exceedances
of SO2 from CHP 3 occurred due to malfunctioning of the control instrument. The
exceedance of Dust, CO, NOx, VOCs and NH3 from ASP occurred due to system
instability caused by the blockage of the stripping column and unstable column
and thermal oxidizer temperature of the ASP.
The
Contractor has implemented mitigation measures to control the exceedance
(including replacement of malfunctioned parts (desulphurisation system, columns
of the ASP), cleaning for various parts (i.e.
stripping column and packaging of the ASP), and carried out fine-tuning of
equipment of the ASP).
The
Contractor is recommended to closely monitor the processes of the modification
of the ASP and the post-modification monitoring of emission level to avoid any
exceedance.
As
similar issues have been re-occurred for sometimes, the Contractor is advised
to undertake a comprehensive review of the operation of the concerned systems
and the effectiveness of the existing mitigation measures and proposed further
measures to avoid the exceedance.
No
odour patrol was required to be conducted for this reporting period.
Non-compliance
of discharge limit of Suspended Solids and Chemical Oxygen Demand, stipulated
in the discharge licence issued by the EPD under the Water Pollution Control
Ordinance, from Petrol Interceptor 2 was recorded during the reporting
period. The Contractor suspected the exceedance to have resulted from the
washing down of food waste residue from the ad-hoc unloading and unpacking of
food waste near the sampling point between mid-November 2021 and early December
2021. The Contractor has scheduled cleaning of the Petrol Interceptor in
January 2022 and will schedule routine cleaning after future ad-hoc pre-processing
work on site.
Waste
generated from the operation of the Project includes chemical waste, waste
generated from pre-treatment process and general refuse.
No
chemical waste was collected by licenced waste collector from the operation of the
Project.
1,012.28
tonnes of waste generated from pre-treatment process from the operation of the
Project was disposed of at landfill. Among the recyclable waste generated
from pre-treatment process from the operation of the Project, 0.00 tonnes of metals,
0.67 tonnes of papers/ cardboard packing and 0.00 tonnes of plastics were sent
to recyclers for recycling during the reporting period.
Around
7.60 tonnes of general refuse from the operation of the Project was disposed of at landfill. Among the recycled
general refuse from the operation of the Project, 0.00 tonnes of metals, 0.00
tonnes of papers/ cardboard packing and 0.00 tonnes of plastics were sent to
recyclers for recycling during the reporting period.
Findings
of Environmental Site Audit
A summary of the monitoring activities undertaken in
this reporting period is listed below:
·
Joint Environmental Site Inspections |
3 times |
·
Landscape & Visual Inspections |
3 times |
Monthly joint environmental site inspections were
carried out. The environmental control/ mitigation measures (related to
air quality, water quality, waste (including land contamination prevention),
hazard-to-life and landscape and visual) recommended in the approved EIA Report
and the EM&A Manual were properly implemented by the Contractor during the
reporting month.
Environmental
Exceedance/Non-conformance/Compliant/Summons and Prosecution
Exceedances for the air emission limits for the CHP
and ASP stacks were recorded during the reporting period.
No
complaint/ summon/prosecution was received in this reporting period.
Future
Key Issues
Activities
to be undertaken in the next reporting month include:
·
Operation of the Project.
·
Modification of the CHP and ASP to control the air
emission.
ERM-Hong Kong, Limited (ERM) was
appointed by OSCAR Bioenergy Joint Venture (the Contractor) as the
Environmental Team (ET) to undertake the construction Environmental Monitoring
and Audit (EM&A) programme for the Contract No. EP/SP/61/10 of
Organic Waste Treatment Facilities Phase I, which the project name has
been updated to Organic Resources Recovery Centre (Phase I) (the Project)
since November 2017. ERM was also appointed by the
Contractor to undertake the operation EM&A programme starting 1 March 2019.
This is the 27th
Quarterly EM&A report which summarises the monitoring results and audit
findings for the EM&A programme during the reporting period from 1
December 2021 to 28 February 2022.
The structure of the report is as
follows:
Section 1: Introduction
It details the
scope and structure of the report.
Section
2: Project Information
It summarises
the background and scope of the Project, site description, project organisation
and status of the Environmental Permits (EP)/licences.
Section
3: Environmental Monitoring and Audit Requirements
It summarises
the environmental monitoring requirements including monitoring parameters,
programmes, methodologies, frequency, locations, Action and Limit Levels,
Event/Action Plans, as well as environmental audit requirements as recommended
in the EM&A Manual and approved EIA report.
Section
4: Monitoring Results
It summarises
monitoring results of the reporting period.
Section
5: Site Audit
It summarises
the audit findings of the environmental as well as landscape and visual site
audits undertaken within the reporting period.
Section
6: Environmental Non-conformance
It summarises
any exceedance of environmental performance standard, environmental complaints
and summons received within the reporting period.
Section
7: Further Key Issues
It summarises
the impact forecast for the next reporting month.
Section
8: Conclusions
The Organic Resources Recovery
Centre (ORRC) Phase I development (hereinafter referred to as “the Project”) is
to design, construct and operate a biological treatment facility with a
capacity of about 200 tonnes per day and convert source-separated organic waste
from commercial and industrial sectors (mostly food waste) into compost and
biogas through proven biological treatment technologies. The location of
the Project site is shown in Annex
A.
The environmental
acceptability of the construction and operation of the Project had been
confirmed by findings of the associated Environmental Impact Assessment (EIA)
Study completed in 2009. The Director of Environmental Protection (DEP)
approved this EIA Report under the Environmental Impact Assessment Ordinance
(EIAO) (Cap. 499) in February 2010 (Register No.: AEIAR-149/2010) (hereafter referred to as the approved EIA Report).
Subsequent Report on Re-assessment on Environmental Implications and Report on
Re-assessment on Hazard to Life Implications were completed in 2013,
respectively.
An Environmental Permit
(EP) (No. EP-395/2010) was issued by
the DEP to the EPD (Project Team), the Permit Holder, on 21 June 2010 and
varied on 18 March 2013 (No. EP-395/2010/A) and 21 May 2013 (No.
EP-395/2010/B), respectively. The Design Build and Operate Contract for
the ORRC Phase 1 (Contract No. EP/SP/61/10 Organic Resources Recovery Centre
(Phase 1) (the Contract)) was awarded to SITA Waste Services Limited, ATAL
Engineering Limited and Ros-Roca, Sociedad Anonima
jointly trading as the OSCAR Bioenergy Joint Venture (OSCAR or the
Contractor). A Further EP (No. FEP-01/395/2010/B) was issued by the DEP
to the OSCAR on 16 February 2015. Variation to both EPs (Nos.
EP-395/2010/B and FEP-01/395/2010/B) were made in December 2015. The
latest EPs, Nos. EP-395/2010/C and FEP-01/395/2010/C, were issued by the DEP on
21 December 2015.
Under the requirements
of Condition 5 of the EP (No. FEP-01/395/2010/C), an Environmental Monitoring
and Audit (EM&A) programme as set out in the approved EM&A Manual
(hereinafter referred to as EM&A Manual) is required to be implemented
during the construction and operation of the Project. ERM-Hong Kong, Ltd
(ERM) has been appointed by OSCAR as the Environmental Team (ET) for the
construction phase EM&A programme and the Monitoring Team (MT) for the
operation phase EM&A programme for the implementation of the EM&A programme
in accordance with the requirements of the EP and the approved EM&A Manual.
The
construction works commenced on 21 May 2015. The operation phase of the
EM&A programme commenced on 1 March 2019 ([1]). The
construction phase EM&A programme was completed in the end of February
2020.
The Project Site is located at Siu
Ho Wan in North Lantau with an area of about 2 hectares. The layout of
the Project Site is illustrated in Annex A. The facility received an average of
106.22 to 129 tonnes and treated an average of 96.91 to 116 tonnes of source
separated organic waste per day during the reporting month.
A summary of the major activities
undertaken in the reporting period is shown in Table 2.1.
Table 2.1
Summary of Activities Undertaken in the Reporting Period
Activities
Undertaken in the Reporting Period |
·
Systems
being operated – waste reception, pre-treatment, CAPCS extraction, the
digesters, the centrifuge, the composting tunnels, the desulphurisation, the
emergency flare, the CHPs, the ASP and the biological waste
water treatment plant (about 106.22 - 129 t/d SSOW input); and ·
Process
fine-tune – adjustment of the ASP operational parameters with new treatment
media, CEMS/SCADA modification and improvement work following equipment
failures and the alteration of different operation modes and measures to adapt
to the high variation of SSOW nature and sources. |
The project organisation chart and
contact details are shown in Annex
B.
A summary of the valid permits,
licences, and/or notifications on environmental protection for this Project is
presented in Table 2.2.
Table
2.2
Summary of Environmental Licensing, Notification and Permit Status
Permit/ Licences/ Notification |
Reference |
Validity Period |
Remarks |
Environmental Permit |
FEP-01/395/2010/C |
Throughout the Contract |
Permit granted on 21 December 2015 |
Notification of Construction Works under the Air
Pollution Control (Construction Dust) Regulation |
Ref No. 386715 |
Throughout the Contract |
- |
Effluent Discharge License |
WT00024352-2016 |
3 June 2016 – 30 June 2021 |
Approved on 3 June 2016 |
Effluent Discharge License |
WT00038391-2021 |
7 July 2021 – 30 June 2026 |
Approved on 7 July 2021 |
Chemical Waste Producer Registration |
WPN 5213-961-O2231-01 |
Throughout the Contract |
Approved on 29 April 2015 |
Chemical Waste Producer
Registration |
WPN 5213-961-O2231-02 |
Throughout the implementation of
the Project |
Approved on 10 November 2017 |
Waste Disposal Billing Account |
Account number: 702310 |
Throughout the Contract |
- |
The air quality
(including odour) monitoring to be carried out during the operation phase of
the Project are described below. Although water quality monitoring is not
required for the operation phase under the EM&A programme, there are water
quality monitoring requirement under the Water Discharge Licence of the plant
under the Water Pollution Control Ordinance (WPCO). As part of
this EM&A programme, the monitoring results will be reviewed to check the
compliance with the WPCO requirements.
According to the EM&A Manual
and EP requirements, stack monitoring are required
during the operation phase of the Project.
On-line monitoring (using
continuous environmental monitoring system (CEMS) shall be carried out for the
centralised air pollution unit (CAPCS), cogeneration units (CHP) and the
ammonia stripping plant (ASP) during the operation phase. The last
calibration was carried out on 15 June 2021.
The monitoring data is transmitted
instantaneously to EPD (Regional Office) by telemetry system.
When the on-line monitoring for certain
parameter cannot be undertaken, monitoring will be carried out using the
following methodology approved by the EPD.
Table 3.1
Sampling and Laboratory Analysis Methodology
Parameters |
Method |
Stacks to be Monitored |
Gaseous and vaporous organic substances (including methane) |
USEPA Method 18 |
·
CAPCS ·
CHP ·
ASP |
Particulate |
USEPA Method 5 |
·
CAPCS ·
CHP ·
ASP |
Carbon monoxide (CO) |
USEPA Method 10 |
·
CHP ·
ASP |
Nitrogen oxides (NOx) |
USEPA Method 7E |
·
CHP ·
ASP |
Sulphur dioxide (SO2); |
USEPA Method 6 |
·
CHP ·
ASP |
Hydrogen chloride (HCl) |
USEPA Method 26A |
·
CHP ·
ASP |
Hydrogen fluoride (HF) |
USEPA Method 26A |
·
CHP ·
ASP |
Oxygen (O2); |
USEPA Method 3A |
·
CAPCS ·
CHP ·
ASP |
Velocity and Volumetric Flow |
USEPA Method 2 |
·
CAPCS ·
CHP ·
ASP |
Ammonia (NH3) |
USEPA CTM 027 |
·
ASP |
Odour (including NH3 and H2S) |
EN 13725 |
·
CAPCS |
Water vapour content (continuous measurement of the water vapour
content should not be required if the sample exhaust gas is dried before the
emissions are analysed) |
USEPA Method 4 |
·
CAPCS ·
CHP ·
ASP |
Temperature |
USEPA Method 4 |
·
CAPCS ·
CHP ·
ASP |
With reference to the EM&A
Manual, the air emission of the stacks shall meet the following emission limits
as presented in Tables 3.2 to 3.5.
Table 3.2
Emission Limit for CAPCS Stack
Parameter |
Emission Level (mg/Nm3) (a) |
VOCs (including methane) |
680 |
Dust (or Total Suspended Particulates (TSP)) |
6 |
Odour (including NH3 & H2S) |
220 (b) |
Notes:
(a)
Hourly average concentration (b)
The odour unit is OU/Nm3 |
Table 3.3
Emission Limit for CHP Stack
Parameter |
Maximum Emission Level (mg/Nm3) (a) (b) |
Dust (or Total Suspended Particulates) |
15 |
Carbon Monoxide |
650 |
NOx |
300 |
SO2 |
50 |
NMVOCs (c) |
150 |
VOCs (including methane) (d) |
1,500 |
HCl |
10 |
HF |
1 |
Notes:
(a) All values refer to an oxygen content in
the exhaust gas of 6% and dry basis. (b) Hourly average concentration (c) NMVOCs should be monitored by gas sampling
and laboratory analysis at an agreed interval. For the first 12 months
(starting from August 2019), monitoring should be carried out at quarterly
intervals. The monitoring frequency should then be reduced to half-yearly for
next 12 months (starting from August 2020). (d) The VOCs emission limit include methane as
biogas is adopted as fuel in the combustion process. |
Table 3.4
Emission Limit for ASP Stack
Parameter |
Maximum Emission Level (mg/Nm3) (a) (b) |
Dust (or Total Suspended Particulates) |
5 |
Carbon Monoxide |
100 |
NOx |
200 |
SO2 |
50 |
VOCs (including methane) (c) |
20 |
NH3 |
35 |
HCl |
10 |
HF |
1 |
Notes: (a)
All values refer to an oxygen content in the exhaust gas of 11% and
dry basis. (b)
Hourly average concentration (c)
The VOCs emission limit include methane as biogas is adopted as fuel
in the combustion process. |
Table
3.5 Emission Limit for Standby
Flaring Gas Unit ([2])
Parameter |
Maximum Emission level (mg/Nm3) (a) (b) |
Dust (or Total Suspended Particulates) |
5 |
Carbon Monoxide |
100 |
NOx |
200 |
SO2 |
50 |
VOCs (including methane) (c) |
20 |
HCl |
10 |
HF |
1 |
Notes: (a)
All values refer to an oxygen content in the exhaust gas of 11% and
dry basis. (b)
Hourly average concentration (c)
The VOCs emission limit include methane as biogas is adopted as fuel
in the combustion process. |
To
determine the effectiveness of the proposed odour mitigation measures and to
ensure that the operation of the ORRC1 will not cause adverse odour impacts,
odour monitoring of the CAPCS stack (see Section 3.1.1)
and odour patrol will be carried out.
Odour patrol shall be conducted by
independent trained personnel/ competent persons in summer months (i.e. from July to September) for the first two operational
years of ORRC1 at monthly intervals along an odour patrol route at the Project
Site boundary as shown in Annex
A.
The perceived odour intensity is
divided into 5 levels. Table 3.6 describes the odour intensity for
different levels.
Table 3.6
Odour Intensity Level
Level |
Odour Intensity |
0 |
Not detected. No odour
perceived or an odour
so weak that it cannot be easily
characterised or described |
1 |
Slight identifiable odour, and slight chance
to have odour nuisance |
2 |
Moderate identifiable odour, and moderate chance to
have odour nuisance |
3 |
Strong identifiable, likely to have odour nuisance |
4 |
Extreme severe odour, and unacceptable odour level |
Table 3.7
shows the action level and limit level to be used for odour patrol. Should any exceedance
of the action and limit levels occurs, actions in accordance with the event and
action plan in Table 3.8 should be carried out.
Table 3.7
Action and Limit Levels for Odour Nuisance
Parameter |
Action Level |
Limit Level |
Odour Nuisance (from odour patrol) |
When one documented compliant is received (a), or Odour Intensity
of 2 is measured
from odour patrol. |
Two or more documented complaints
are received (a) within a week; or Odour intensity of 3 or above is measured
from odour patrol. |
Note:
(a)
Once the complaint is received by the Project Proponent (EPD), the
Project Proponent would investigate and verify the complaint whether it is
related to the potential odour emission from the ORRC1 and its on-site
wastewater treatment unit. |
Table 3.8
Event and Action Plan for Odour Monitoring
Event |
Action |
|
|
Person-in-charge of Odour Monitoring |
Project Proponent (a) |
Action Level |
|
|
Exceedance of action level (Odour Patrol) |
1. Identify source/reason of exceedance; 2. Repeat odour patrol to confirm finding. |
1. Carry out investigation to identify the source/reason of
exceedance. Investigation should be completed within 2 weeks; 2. Rectify any unacceptable practice; 3. Implement more mitigation measures if necessary; 4. Inform Drainage Services Department (DSD) or the operator of the
Siu Ho Wan Sewage Treatment Works (SHWSTW) if exceedance is
considered to be caused by the operation of the SHWSTW. 5. Inform North Lantau Refuse Transfer Station (NLTS) operator if
exceedance is considered to be caused by the
operation of NLTS. |
Exceedance of action level (Odour Complaints) |
1. Identify source/reason of exceedance; 2. Carry out odour patrol to determinate odour intensity. |
1. Carry out investigation and verify the complaint whether it is
related to potential odour emission from the nearby SHWSTW; 2. Carry out investigation to identify the source/reason of
exceedance. Investigation should be completed within 2 weeks; 3. Rectify any unacceptable practice; 4. Implement more mitigation measures if necessary; 5. Inform DSD or the operator of the SHWSTW if exceedance is considered to be caused by the operation of the SHWSTW. 6. Inform NLTS operator if exceedance is considered
to be caused by the operation of NLTS. |
Limit Level |
|
|
Exceedance of limit level |
1. Identify source/reason of exceedance; 2. Inform EPD; 3. Repeat odour patrol to confirm findings; 4. Increase odour patrol frequency to bi-weekly; 5. Assess effectiveness of remedial action and keep EPD informed of
the results; 6. If exceedance stops, cease additional odour patrol. |
1. Carry out investigation to identify the source/reason of
exceedance. Investigation should be completed within 2 week; 2. Rectify any unacceptable practice; 3. Formulate remedial actions; 4. Ensure remedial actions properly implemented; 5. If exceedance continues, consider what more/enhanced mitigation
measures should be implemented; 6. Inform DSD or the operator of the SHWSTW if exceedance is considered to be caused by the operation of the
SHWSTW. |
Note:
(a)
Project Proponent shall identify an implementation agent. |
Environmental mitigation measures
(related to air quality, water quality, waste, land contamination,
hazard-to-life, and landscape and visual) to be implemented during the
operation phase of the Project are recommended in the approved EIA Report and
EM&A Manual and are summarised in Annex C. Monthly site audits for operation phase
will be carried out to check the implementation of these measures.
Compliance audits are to be
undertaken to ensure that a valid discharge licence has been issued by EPD
prior to the discharge of effluent from the operation of the Project
site. Under Effluent Discharge Licence WT00038391-2021 (effective from
July 2021), the effluent quality shall meet the discharge limits as described
in Table 3.9 and Table 3.10.
Table 3.9
Discharge Limits for Effluent from the Effluent Storage Tank (as
stipulated in WT00038391-2021)
Parameters |
Discharge Limit (mg/L) |
Flow Rate (m3/day) (a) |
645 |
pH (pH units) (b) |
6-10 (c) |
Suspended Solids (b) |
800 |
Biochemical Oxygen Demand (5 days, 20°) (b) |
800 |
Chemical Oxygen Demand (b) |
2,000 |
Oil & Grease (b) |
40 |
Total Nitrogen (b) |
200 |
Total Phosphorus (b) |
50 |
Surfactants (total) (b) |
25 |
Notes: (a)
Flow rate is not a parameter required to be monitored and reported by
the Contractor in accordance to Section B2 of the
Effluent Discharge Licence under the WPCO. (b)
Parameters required to be monitored and reported by the Contractor in
accordance to Section B2 of the Effluent Discharge
Licence under the WPCO. (c)
Range. |
Table
3.10 Discharge
Limits for Effluent from
the Petrol Interceptor(s) (as stipulated in WT00038391-2021)
Discharge Limit (mg/L) |
|
Flow Rate (m3/day) |
245 (a) |
Suspended Solids (b) |
30 |
Chemical Oxygen Demand (c) |
80 |
Oil & Grease (c) |
20 |
Surfactants (total) (b) |
15 |
Notes: (a)
The surface runoff flow rate limit was estimated by the overall yearly
rainfall data. As the actual flowrate from the petrol interceptors
depends on the weather condition instead of the performance of the petrol
interceptor, monitoring and reporting of this parameter is not required.
Hence this parameter is not reported in Table 4.9., Table
4.10., Table 4.11 and Table 4.12. (b)
Parameter not required to be reported in accordance to
Section B2 of the Effluent Discharge Licence under the WPCO. (c)
Parameters required to be reported in accordance to
Section B2 of the Effluent Discharge Licence under the WPCO. |
In accordance with EM&A Manual,
the landscape and visual mitigation measures shall be implemented.
For operation phase, site
inspection shall be conducted once a month for the first year of operation of
the Project. All measures as stated in the implementation schedule of the
EM&A Manual (see Annex C),
including compensatory planting, undertaken by both the Contractor and the
specialist Landscape Sub-Contractor during the first year of the operation
phase shall be audited by a Registered Landscape Architect (RLA) to ensure
compliance with the intended aims of the measures and the effectiveness of the
mitigation measures.
The concentrations of concerned air
pollutants emitted from the stacks of the CAPCS, CHP, and ASP during the
reporting period are monitored on-line by the continuous environmental
monitoring system (CEMS). During the reporting period, the standby flare
operated on 7, 29 Dec 2021 and 28 Jan 2022.
With reference to the emission
limits shown in Tables 3.2, 3.3 and 3.4, the hourly average
concentrations and the number of exceedances of the concerned air emissions
monitored for the CAPCS, CHP and ASP during this reporting period are presented
in Tables 4.1 to 4.5.
It should be noted that
measurements recorded under abnormal operating conditions, e.g.
start up and stopping of stacks, unstable operation, test runs and interference
of sensor, are disregarded.
Table 4.1
Hourly Average of Parameters Recorded for CAPCS
Parameter |
Range of Hourly Average Conc. (mg/Nm3) |
Emission Limit (mg/Nm3) |
Exceedance Identified |
Remarks |
VOCs (including methane) |
0.00 – 23.73 |
680 |
Nil |
Nil |
Dust (or TSP) |
0.00 – 0.02 |
6 |
Nil |
Nil |
Odour (including NH3 & H2S) (a) |
0.00 – 200.29 |
220 |
Nil |
Nil |
Note: (a)
The odour unit is OU/Nm3. |
Table 4.2
Hourly Average of Parameters Recorded for CHP 1
Parameter |
Range of Hourly Average Conc. (mg/Nm3)
(a) |
Max. Emission Limit (mg/Nm3) |
Exceedance Identified |
Remarks |
Dust (or TSP) |
0 -
2 (b) |
15 |
Nil |
Nil |
Carbon Monoxide |
0 -
634 (b) |
650 |
Nil |
Nil |
NOx |
0 -
292 (b) |
300 |
Nil |
Nil |
SO2 |
0 - 34 (b) |
50 |
Nil |
Nil |
VOCs (including methane) (c) |
0 - 1,485 (b) |
1,500 |
Nil |
Nil |
HCl |
0 - 2 (b) |
10 |
Nil |
Nil |
HF |
0 - 1 (b) |
1 |
Nil |
Nil |
Notes: (a)
All values refer to an oxygen content in the exhaust gas of 6%
and dry basis. (b)
CHP 1 was shut down in December 2021 for maintenance and preparation
of overhaul. (c)
The VOCs emission limit include methane as biogas is adopted as fuel
in the combustion process. |
Table 4.3
Hourly Average of Parameters Recorded for CHP 2
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a) |
Max. Emission Limit (mg/Nm3) |
Exceedance Identified |
Remarks |
Dust (or TSP) |
0 – 15 |
15 |
Nil |
Nil |
Carbon Monoxide |
0 – 446 |
650 |
Nil |
Nil |
NOx |
0 – 300 |
300 |
Nil |
Nil |
SO2 |
0 – 42 |
50 |
Nil |
Nil |
VOCs (including methane) (b) |
0 – 1,438 |
1,500 |
Nil |
Nil |
HCl |
0 – 1.95 |
10 |
Nil |
Nil |
HF |
0 – 1 |
1 |
Nil |
Nil |
Notes: (a)
All values refer to an oxygen content in the exhaust gas of 6%
and dry basis. (b)
The VOCs emission limit include methane as biogas is adopted as fuel
in the combustion process. |
Table 4.4
Hourly Average of Parameters Recorded for CHP 3
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a) |
Max. Emission Limit (mg/Nm3) |
Exceedances Identified |
Remarks |
Dust (or TSP) |
0 – 14 |
15 |
Nil |
Nil |
Carbon Monoxide |
0 – 593 |
650 |
Nil |
Nil |
NOx |
0 – 405 |
300 |
Identified (c) |
System unstable (e.g. low efficiency, unstable column temperature ) |
SO2 |
0 – 61 |
50 |
Identified (d) |
Desulpurisation system
tripped |
VOCs (including methane) (b) |
0 – 1,151 |
1,500 |
Nil |
Nil |
HCl |
0 – 6 |
10 |
Nil |
Nil |
HF |
0 – 1 |
1 |
Nil |
Nil |
Notes: (a) All values refer to
an oxygen content in the exhaust gas of 6% and dry basis. (b) The VOCs emission
limit include methane as biogas is adopted as fuel in the combustion
process. (c)
Dates with exceedances on
NOx
(number of exceedances on
the day) were identified on 1 (1), 13 (1), 21 (6), 22 (8), 23 (16), 24 (8)
and 29 (7) January 2022. (d)
Date with exceedances on
SO2
(number of exceedance on the day) was identified on 19 (2) December
2021 and 23 (2) February 2022. |
Table 4.5
Hourly Average of Parameters Recorded for ASP
Parameter |
Range of Hourly Average Conc. (mg/Nm3) (a) |
Max. Emission Limit (mg/Nm3) |
Exceedances Identified |
Remarks |
Dust (or TSP) |
0 – 11 |
5 |
Identified (c) |
System unstable (e.g. low efficiency, unstable column temperature ) |
Carbon Monoxide |
0 – 575 |
100 |
Identified (d) |
System unstable (e.g. low efficiency, unstable column temperature ) |
NOx |
0 – 439 |
200 |
Identified (e) |
System unstable (e.g. low efficiency, unstable column temperature ) |
SO2 |
0 – 76 |
50 |
Identified (f) |
Desulpurisation system
tripped |
VOCs (including methane) (b) |
0 – 2,793 |
20 |
Identified (g) |
System unstable (e.g. low efficiency, unstable column temperature ) |
NH3 |
0 – 268 |
35 |
Identified (h) |
System unstable (e.g. low efficiency, unstable column temperature ) |
HCl |
0 – 2 |
10 |
Nil |
Nil |
HF |
0 – 1 |
1 |
Nil |
Nil |
Notes: (a)
All values refer to an oxygen content in the exhaust gas of 11% and
dry basis. (b)
The VOCs emission limit include methane as biogas is adopted as fuel
in the combustion process. (c)
Date with exceedances on dust (number of exceedances on the day) was
identified on 8 (1)
February 2022. (d)
Date with exceedances on CO (number of exceedances on the day) were
identified on 5 (2) January and 6 (1) February 2022. (e)
Date with exceedances on NOx (number of exceedances on the day) were
identified on 1 (1), 2 (2), 6 (1), 7 (2), 8 (8), 9 (9), 14 (14), 15 (12), 16
(3), 21 (3), 23 (2), 24 (7), 25 (1), 27 (6), 28 (1), 29 (4) and 31 (1)
December 2021; 4 (1), 5 (1), 6 (1), 9 (1), 10 (1), 11 (2), 28 (1), 30 (19)
and 31 (19) January 2022; 1 (3), 2 (3), 3 (11), 4 (7), 5 (1), 6 (2), 8 (3), 9
(1), 10 (3), 11 (1), 12 (1), 13 (2), 14 (2), 18 (1), 21 (8) and 28 (9)
February 2022. (f)
Dates with exceedances on SO2 (number of exceedances on the
day) were identified on 24 (6), 25 (2) and 29 (4) December 2021. (g)
Dates with exceedances on VOCs (number of exceedances on the day) were
identified on 1 (1) December 2021; 5 (2) January 2022; 6 (1), 8 (1) and 9 (1)
February 2022. (h)
Dates with exceedances on NH3 (number of exceedances on the
day) were identified on 3 (2), 4 (2), 10 (1), 11 (1), 12 (1), 15 (1), 17 (1),
19 (3), 20 (5), 21 (2), 23 (5), 24 (1), 25 (1) and 31 (3) December 2021; 6
(1), 7 (1), 8 (1), 9 (3), 10 (4), 11 (7), 12 (1), 27 (1), 28 (10), 29 (3), 30
(3) and 31 (1) January 2022; 1 (6), 2 (6), 3 (2), 6 (2), 7 (4), 8 (7), 9 (1),
11 (3), 12 (9), 13 (11), 14 (3), 15 (10), 16 (11), 17 (5), 18 (1), 19 (10)
and 20 (12) February 2022. |
No odour patrol was required to be
conducted for this reporting period.
Effluent discharge was sampled
monthly from the Effluent Storage Tank as stipulated in the operation phase
discharge licence. Discharge from the Petrol Interceptors were sampled
bi-monthly since July 2021 as stipulated in the operation phase discharge
licence. The results of the discharge samples from the Effluent Storage
Tank are recorded in Table 4.6 to 4.8. The results of the
discharge samples from the Petrol Interceptors are recorded in Table 4.9 to
4.12.
Table 4.6
Results of the Discharge Sample Collected from the Effluent Storage Tank in
December 2021
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Flow Rate (m3/day) (a) |
50 - 268 (e) |
645 |
Yes |
pH (pH units) (b) |
7.94 – 8.28 (e) |
6-10 (c) |
Yes |
Suspended Solids (b) (d) |
196 (d) |
800 |
Yes |
Biochemical Oxygen Demand (5 days, 20°) (b) (d) |
72 (d) |
800 |
Yes |
Chemical Oxygen Demand (b)
(d) |
1,110 (d) |
2,000 |
Yes |
Oil & Grease (b) (d) |
<5 (d) |
40 |
Yes |
Total Nitrogen (b) (d) |
83.6 (d) |
200 |
Yes |
Total Phosphorus (b) (d) |
22.8 (d) |
50 |
Yes |
Surfactants (total) (b) (d) |
1.2 (d) |
25 |
Yes |
Notes: (a)
Parameter not required to be reported in accordance to
Section B2 of the Effluent Discharge Licence under the WPCO. (b)
Parameters required to be reported in accordance to
Section B2 of the Effluent Discharge Licence under the WPCO. (c)
Daily Range. (d)
Effluent sample collected on 20 December 2021. (e)
Data collected daily in the reporting month. |
Table 4.7
Results of the Discharge Sample Collected from the Effluent Storage Tank in
January 2022
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Flow Rate (m3/day) (a) |
0 - 215
(e) |
645 |
Yes |
pH (pH units) (b) |
7.86 – 8.28
(e) |
6-10 (c) |
Yes |
Suspended Solids (b) (d) |
108 (d) |
800 |
Yes |
Biochemical Oxygen Demand (5 days, 20°) (b) (d) |
54 (d) |
800 |
Yes |
Chemical Oxygen Demand (b)
(d) |
1,040
(d) |
2,000 |
Yes |
Oil & Grease (b) (d) |
<5 (d) |
40 |
Yes |
Total Nitrogen (b) (d) |
71.8 (d) |
200 |
Yes |
Total Phosphorus (b) (d) |
14.2
(d) |
50 |
Yes |
Surfactants (total) (b) (d) |
2.1
(d) |
25 |
Yes |
Notes: (a)
Parameter not required to be reported in accordance to
Section B2 of the Effluent Discharge Licence under the WPCO. (b)
Parameters required to be reported in accordance to
Section B2 of the Effluent Discharge Licence under the WPCO. (c)
Daily Range. (d)
Effluent sample collected on 7 January 2022. (e)
Data collected daily in the reporting month. |
Table 4.8
Results of the Discharge Sample Collected from the Effluent Storage Tank in
February 2022
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Flow Rate (m3/day) (a) |
0 – 301
(e) |
645 |
Yes |
pH (pH units) (b) |
7.70 – 8.25 (e) |
6-10 (c) |
Yes |
Suspended Solids (b) (d) |
203 (d) |
800 |
Yes |
Biochemical Oxygen Demand (5 days, 20°) (b) (d) |
101 (d) |
800 |
Yes |
Chemical Oxygen Demand (b)
(d) |
1,440
(d) |
2,000 |
Yes |
Oil & Grease (b) (d) |
<5 (d) |
40 |
Yes |
Total Nitrogen (b) (d) |
108 (d) |
200 |
Yes |
Total Phosphorus (b) (d) |
23.2 (d) |
50 |
Yes |
Surfactants (total) (b) (d) |
<1.0
(d) |
25 |
Yes |
Notes: (a)
Parameter not required to be reported in accordance to
Section B2 of the Effluent Discharge Licence under the WPCO. (b)
Parameters required to be reported in accordance to
Section B2 of the Effluent Discharge Licence under the WPCO. (c)
Daily Range. (d)
Effluent sample collected on 11 February 2022. (e)
Data collected daily in the reporting month. |
Table 4.9
Results of the Discharge Sample from the Petrol Interceptor 1 on 9
December 2021
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Suspended Solids (b) |
9 (a) |
30 |
Yes |
Chemical Oxygen Demand (c) |
41 (a) |
80 |
Yes |
Oil & Grease (c) |
<5 (a) |
20 |
Yes |
Surfactants (total) (b) |
<1.0 (a) |
15 |
Yes |
Notes: (a)
Effluent sample collected on 9 December 2021. (b)
Parameter not required to be reported in accordance to
Section B2 of the Effluent Discharge Licence under the WPCO. (c)
Parameters required to be reported in accordance to
Section B2 of the Effluent Discharge Licence under the WPCO. |
Table
4.10 Results
of the Discharge Sample from the Petrol Interceptor 1 on 16 February 2022
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Suspended Solids (b) |
<2
(a) |
30 |
Yes |
Chemical Oxygen Demand (c) |
<5
(a) |
80 |
Yes |
Oil & Grease (c) |
<5 (a) |
20 |
Yes |
Surfactants (total) (b) |
<1 (a) |
15 |
Yes |
Notes: (a)
Effluent sample collected on 16 February 2022. (b)
Parameter not required to be reported in accordance to
Section B2 of the Effluent Discharge Licence under the WPCO. (c)
Parameters required to be reported in accordance to
Section B2 of the Effluent Discharge Licence under the WPCO. |
Table 4.11
Results of the Discharge Sample from the Petrol Interceptor 2 on 9 December
2021
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Suspended Solids (b) |
34 (a) |
30 |
No |
Chemical Oxygen Demand (c) |
167 (a) |
80 |
No |
Oil & Grease (c) |
6 (a) |
20 |
Yes |
Surfactants (total) (b) |
<1.0 (a) |
15 |
Yes |
Notes: (a)
Effluent sample collected on 9 December 2021. (b)
Parameter not required to be reported in accordance to
Section B2 of the Effluent Discharge Licence under the WPCO. (c)
Parameters required to be reported in accordance to
Section B2 of the Effluent Discharge Licence under the WPCO. |
Table 4.12
Results of the Discharge Sample from the Petrol Interceptor 2 on 16 February
2022
Parameters |
Discharged Effluent Concentration (mg/L) |
Discharge Limit (mg/L) |
Compliance with Discharge Limit |
Suspended Solids (b) |
<2 (a) |
30 |
Yes |
Chemical Oxygen Demand (c) |
6 (a) |
80 |
Yes |
Oil & Grease (c) |
<5 (a) |
20 |
Yes |
Surfactants (total) (b) |
<1 (a) |
15 |
Yes |
Notes: (a)
Effluent sample collected on 16 February 2022. (b)
Parameter not required to be reported in accordance to
Section B2 of the Effluent Discharge Licence under the WPCO. (c)
Parameters required to be reported in accordance to
Section B2 of the Effluent Discharge Licence under the WPCO. |
Non-compliance of discharge limit
of Suspended Solids and Chemical Oxygen Demand from Petrol Interceptor 2 was
recorded during the reporting period.
Wastes generated from the operation
of the Project include chemical waste, wastes generated from pre-treatment
process and general refuse ([3]).
Reference has been made to the Monthly Summary Waste Flow Table prepared by the
Contractor (see Annex D).
With reference to the relevant handling records and trip tickets of this
Project, the quantities of different types of waste generated from the
operation of the Project in the reporting month are summarised in Table 4.13.
Table 4.13
Quantities of Waste Generated from the Operation of the Project
Month / Year |
Chemical Waste |
Waste Generated from |
General Refuse |
||
|
Disposal of at CWTC (e) |
Disposed of at Landfill (a) |
Recycled (b) |
Disposed of at Landfill (a) (c) |
Recycled (d) |
December 2021 |
0 L |
392.44 tonnes |
0.67 tonnes |
2.53 tonnes |
0.00 tonne |
January 2022 |
0 L |
359.27 tonnes |
0.00 tonnes |
2.65 tonnes |
0.00 tonne |
February 2022 |
0 L |
260.57 tonnes |
0.00 tonnes |
2.42 tonnes |
0.00 tonne |
Notes: (a)
Waste
generated from pre-treatment process and general refuse other than chemical
waste and recyclables were disposed of at NENT landfill by sub-contractors. (b)
Among waste generated from pre-treatment process, 0.00 tonne of
metals, 0.67 tonne of papers/ cardboard packing and 0.00 tonne of plastics
were sent to recyclers for recycling during the reporting period. (c)
It was assumed that four 240-litre bins filled with 80% of general
refuse were collected at each collection. The general refuse density
was assumed to be around 0.15 kg/L. (d)
Among general refuse, 0.00 tonnes of metals, 0.00 tonnes of papers/
cardboard packing and 0 tonnes of plastics were sent to recyclers for
recycling during the reporting period. (e)
No chemical waste was generated in this reporting period. |
The
monthly inspections of the operation phase of the Project covered the operation
phase environmental site inspections. The inspections checked the
implementation of the recommended mitigation measures for air quality,
landscape and visual, water quality, waste (land contamination) and
hazard-to-life stated in the Implementation Schedule (see Annex C).
Follow-up
actions resulting from the site inspections were generally taken as reported by
the Contractor. The Contractor has implemented environmental mitigation
measures recommended in the approved EIA Report and EM&A Manual.
December
2021
The
monthly inspection of the operation phase of the Project on 10 December 2021
covered the operation phase environmental site audit. Joint site
inspections was conducted by representatives of the
Contractor, IEC and the MT on 10 December 2021 as required for the operation of
the Project.
January
2022
The
monthly inspection of the operation phase of the Project on 6 January 2022
covered the operation phase environmental site audit. Joint site
inspections was conducted by representatives of the
Contractor, IEC and the MT on 6 January 2022 as required for the operation of
the Project.
February
2022
The
monthly inspection of the operation phase of the Project on 14 February 2022 covered the
operation phase environmental site audit. Joint site inspections was conducted by representatives of the Contractor, IEC and
the MT on 14 February 2022
as required for the operation of the Project.
It was confirmed that the necessary
landscape and visual mitigation measures during the operation phase as
summarised in Annex C
were generally implemented by the Contractor. No non-compliance in
relation to the landscape and visual mitigation measures was identified during
the site audits in this reporting period and therefore no further actions are
required. The ET/MT will keep track of the EM&A programme to check
compliance with environmental requirements and the proper implementation of all
necessary mitigation measures.
December 2021
Monthly inspection of the landscape and visual mitigation measures for
the operation phase of the Project was performed on 10 December 2021.
January 2022
Monthly inspection of the landscape and visual mitigation measures for
the operation phase of the Project was performed on 6 January 2022.
February 2022
Monthly inspection of the landscape and visual mitigation measures for
the operation phase of the Project was performed on 14 February 2022.
December 2021
Non-compliance of emission limits
of SO2 from CHP and NOx, SO2, VOCs and NH3
from ASP were recorded during the reporting period.
The Contractor has reviewed the
organic waste treatment processes (i.e. waste
reception, waste pre-treatment, anaerobic digesters, and composting processes)
and found that they were operated normally during the reporting period.
The Contractor has investigated air pollution control systems for the CHP and
ASP and identified several potential causes for the exceedance. Remedial
and follow-up actions had been recommended to the Contractor to perform
accordingly.
Non-compliance of discharge limit
of Suspended Solids and Chemical Oxygen Demand from Petrol Interceptor 2 was recorded
during the reporting period.
The Investigation Report is shown
in Annex F.
January 2022
Non-compliance of emission limits of NOx from CHP and CO, NOx,
VOCs and NH3 from ASP were recorded during the reporting
period.
The Contractor has reviewed the
organic waste treatment processes (i.e. waste
reception, waste pre-treatment, anaerobic digesters, and composting processes)
and found that they were operated normally during the reporting period.
The Contractor has investigated air pollution control systems for the CHP and
ASP and identified several potential causes for the exceedance. Remedial
and follow-up actions had been recommended to the Contractor to perform
accordingly.
The Investigation Report is shown
in Annex F.
February 2022
Non-compliance of emission limits of SO2 from CHP 3 and Dust,
CO, NOx, VOCs and NH3 from ASP were recorded during the
reporting period.
The Contractor has reviewed the
organic waste treatment processes (i.e. waste
reception, waste pre-treatment, anaerobic digesters, and composting processes)
and found that they were operated normally during the reporting period.
The Contractor has investigated air pollution control systems for the CHP and
the ASP and identified several potential causes for the exceedance.
Remedial and follow-up actions had been recommended to the Contractor to
perform accordingly. The Investigation Report is shown in Annex F.
Activities to be undertaken for the
coming reporting period are:
·
Operation of the Project.
·
Modification of the CHP and ASP to control the air
emission.
This EM&A Report presents the
EM&A programme undertaken during the reporting period from 1 December
2021 to 28 February 2022 in accordance with EM&A Manual (Version
F) and requirements of EP (FEP-01/395/2010/C).
For the operation phase,
exceedances of the emission limits for stack monitoring (including CAPCS, CHP
and ASP stacks) were recorded under normal operating conditions during the
reporting period (see Table 8.1).
Table
8.1 Exceedances for Stack
Emissions
Stack |
Exceedances During the Reporting Period |
Centralised Air Pollution Control Unit (CAPCS) |
·
Nil |
Cogeneration Unit (CHP) 1 |
·
Nil |
Cogeneration Unit (CHP) 2 |
·
Nil |
Cogeneration Unit (CHP) 3 |
·
Exceeded emission limit of NOx on 1, 13,
21, 22, 23, 24 and 29 January 2022. ·
Exceeded emission limit of SO2 on 19
December 2021 and 23 February 2022. |
Ammonia Stripping Plant (ASP) |
·
Exceeded emission limit of Dust on 8 February 2022. ·
Exceeded emission limit of CO on 5 January and 6
February 2022. ·
Exceeded emission limit of NOx on 1, 2,
6, 7, 8, 9, 14, 15, 16, 21, 23, 24, 25, 27, 28, 29 and 31 December 2021; 4,
5, 6, 9, 10, 11, 28, 30 and 31 January 2022; 1, 2, 3, 4, 5, 6, 8, 9, 10, 11,
12, 13, 14, 18, 21 and 28 February 2022. ·
Exceeded emission limit of SO2 on 24, 25
and 29 December 2021. ·
Exceeded emission limit of VOCs on 1 December 2021
and 5 January 2022; 6, 8 and 9 February 2022 ·
Exceeded emission limit of NH3 on 3, 4,
10, 11, 12, 15, 17, 19, 20, 21, 23, 24, 25 and 31 December 2021; 6, 7, 8, 9,
10, 11, 12, 27, 28, 29, 30 and 31 January 2022; 1, 2, 3, 6, 7, 8, 9, 11, 12,
13, 14, 15, 16, 17, 18, 19 and 20 February 2022. |
In December 2021, the exceedances
of NOx, VOCs and NH3 from ASP occurred due to system
instability caused by blockage of the stripping column. The
exceedances of SO2 from the desulphurisation system for CHP and ASP
were caused by blockage of the hot water system.
In
January 2022, the exceedances of NOx from CHP 3 occurred due to insufficient
feedstock. The exceedance of CO, NOx, VOCs and NH3
from ASP occurred due to system instability caused by the malfunctioning of the
steam generator.
In
February 2022, the exceedances of SO2 from CHP 3 occurred due to malfunctioning
of the control instrument. The exceedance of Dust, CO, NOx, VOCs and
NH3 from ASP occurred due to system instability caused by the
blockage of the stripping column and unstable column and thermal oxidizer
temperature of the ASP.
The Contractor has replaced
malfunctioned parts (desulphurisation system, columns of the ASP), cleaning for
various parts (i.e. stripping column and packaging of
the ASP), and carried out fine-tuning of equipment of the ASP, the
investigation on the underlying reasons of exceedances in CHP and ASP and the
continuous seeking of better and more feedstock to increase biogas loading and
testing at ASP to optimise combustion efficiency and overall performance.
No non-compliance to the effluent
discharge limit was recorded during this reporting period.
The environmental control
/mitigation measures related to air quality, water quality, waste (including
land contamination prevention), hazard-to-life and landscape and visual
recommended in the approved EIA Report and the EM&A Manual were properly
implemented by the Contractor during the reporting period.
Monthly landscape and visual
monitoring were conducted in the reporting period. The necessary
landscape and visual mitigation measures recommended in the approved EIA Report
were generally implemented by the Contractor.
No complaint/summon/prosecution was
received.
([1])
As some of the minor items are yet to be closed out in March
2019, the construction phase EM&A programme and Operation Phase EM&A
programme were undertaking in parallel in March 2019.